Bridgehampton Electric Vehicle Charging Stations

In July, 2021 the Town entered into an agreement with the New York Power Authority (NYPA) to install four (4) electric vehicle charging stations in an existing municipal parking lot. The construction, installation, and maintenance of the electric vehicle charging stations will be paid for by NYPA and impose no cost to the Town of Southampton. Construction is scheduled to begin on April 26, 2022 and last approximately four (4) weeks to be completed by Memorial Day.

  • Project: Bridgehampton Electric Vehicle Charging Stations
  • Location: Municipal Parking located at 99 School Street, Bridgehampton
  • Managing Department: Municipal Works
  • Estimated Project Cost: $0 to Town – Paid for by New York Power Authority (NYPA)
  • Anticipated Completion: Memorial Day, 2022
Bridgehampton Electric Vehicle Charging Stations

TIME-LINE:

2021 - July – Town enters into agreement with NYPA

2021 - November – Town approves preliminary plans

2022 - March – Town issues required Land Management permits

2022 - April – Construction begins

2022 - May – Anticipated construction completion